The Exchange Build Update July 2022

Over the last month, we have progress with the installation of the precast columns, stairs, and twin wall cores and we are now at level 13 with the concrete floor slab. Mast climbers are being installed to the envelope with SFS, weatherboard, windows and brickwork picking up pace.

Internally we are on level 5 of the fitout with dry lining and MEP at different stages with the joinery and kitchen packages due to commence in next period.

 