The Exchange Build Update July 2021

July marks our fourth month on site at The Exchange. A visit to the site this week has been really exciting as we are able to see the progress that has been made.

The ground remediation and piling works have now been completed. Deep excavations have commenced, allowing for the installation of steel cages to the foundations and pouring the concrete on a weekly basis.

Over the next month we will be progressing the concrete frame structure and ground floor concrete slab.

Keep an eye out for our next update which will include photos of the concrete frame going up.

The tower crane has also been installed early in preparation of the frame progressing.

 