As we return from the Christmas break and progress into the new year, the team at Urban Green have made great progress with works on site. 75% of the lower car park ground slab is now complete as well as the perimeter steel reinforcement which will make up the Car park retaining wall.
Meanwhile, the central lift core has now reached the 8th floor level, which is 50% complete of its total height. In addition to this, the columns and commencement of the Higher car park slab decking are well underway.
Central lift core now at Level 8 and start of the decking with props