Urban Green Build Update February 2022

 

As we progress through February, the team at Urban Green have continued their rapid advancement. The slip form lift core is now complete and is standing proud and we the final concrete pour of the lower Ground Carpark is complete.

 

Urban Green February

Slip form lift core completed and the final pour for the lower ground car park.
 

The formwork for the upper ground car park is underway and is starting to be installed, as well as the steel reinforcement in preparation for the final concrete pour. The team have also completed the ground beams which will make up the single story refuse store and substation units

Urban Green February 2

Steel reinforcement installation and ground Beam completion refuse store and substation units.

Speak to us

For more information on Urban Green, check out our dedicated page:

https://www.heatongroup.co.uk/buy-to-let/manchester/urban-green 

Or contact us directly on:

01942 251945 / info@heatongroup.co.uk

 


Enquiry Form


Articles similar to this

Investing in UK Property from Overseas

Investing in the UK property market has never been so appealing to overseas investors. With favourable stamp duty and interest rates, now is a great time.

Read article

The Exchange Build Update July 2021

Our latest build update for The Exchange. A visit to the site this week has been really exciting as we are able to see the progress that has been made.

Read article

Property Investment Hotspot 2021 – Stockport

Milliners House in Stockport is Heaton Groups newest off plan property investment opportunity. Close to Manchester City Centre.

Read article