Urban Green Build Update December 2021


Our construction team at the Urban Green site have been battling against the extreme weather brought by storm Barra with two weeks of torrential rain and howling wind, however they are continuing to make progress with the huge task of pouring the lower ground floor concrete slab.

 

Urban Green - Build Update December

 Progression of concrete slab 
 

Work is also progressing on the slip form rig to the central communal stair and lift shaft core and they have begun the progressive slide of what will be a 50m high concrete structure.

Urban Green - Build Update December 2

Continuation of the slip form rig

The perimeter retaining wall has also commenced and will progressively follow on in unison with the lower ground floor slab.

Urban Green - Build Update December 3

Perimeter retaining walls and columns

Speak to us

For more information on Urban Green, check out our dedicated page:

https://www.heatongroup.co.uk/buy-to-let/manchester/urban-green 

Or contact us directly on:

01942 251945 / info@heatongroup.co.uk

 


Enquiry Form


Articles similar to this

Investing in UK Property from Overseas

Investing in the UK property market has never been so appealing to overseas investors. With favourable stamp duty and interest rates, now is a great time.

Read article

The Exchange Build Update July 2021

Our latest build update for The Exchange. A visit to the site this week has been really exciting as we are able to see the progress that has been made.

Read article

Property Investment Hotspot 2021 – Stockport

Milliners House in Stockport is Heaton Groups newest off plan property investment opportunity. Close to Manchester City Centre.

Read article