Works are progressing well on site at The Exchange, with the piling works complete and the foundations nearing completion.

 

Untitled design (9)

Aerial view of The Exchange, Preston

 

Ground floor are now being cast progressively and columns are being erected to the underside of the first floor. 

The concrete core bases are constructed and core walls will start to rise later this month with upper floors wrapping the cores progressively.

 

Untitled design (10)

Concrete Core in Block A

 

The design is progressing well with levels 1 - 7 of the concrete frame now fully designed. Columns for levels 1 - 6 have been pre-cast off site to aid the construction.

 

September Columns being erected to block A

Concrete columns being erected to Block A

 

Drainage is installed under the ground floor slabs and the attenuation tank has been installed which is a major element of future disruption avoided.

 

September Drainage and slab prep for block A

Drainage and slab prep for Block A

 