The Exchange Build Update August 2021

This month has been very busy on site at The Exchange. We have now started to use the tower crane to support the team installing the steel cages and pouring of the concrete to the foundations and pile caps to 2/3rds of the building footprint.

 

Copy of Untitled (1)Aerial view of The Exchange, Preston

 

Ongoing works include underground drainage, service ducts, DPM and insulation in preparation for the concrete floor slabs.

In the next period we are aiming to pour the ground floor slabs and commence the installation of the concrete columns from ground to first floor.

 

Copy of Untitled (4)Steelwork being installed to core B ahead of the concrete being poured

 

Copy of Untitled (5)Section of ground floor concrete slab during the pour

 