The Exchange Build Update March 2022

Over the past month, the team at The Exchange  have made good progress on the concrete frame, with the level 7 floor slab poured and temporary works tables being installed to level 8. The double story precast columns from level 7 – 9 and the twin wall to cores level 7 – 8 are also making good progress.

The Exchange Build Update  (1)

The exterior of the building up to level 8

In this period we have also commenced the SFS framework to the ground floor, progressed the blockwork walls with curtain walling and windows due to commence in the coming weeks.

The Exchange Build Update 2

 

 