The Exchange Build Update January 2022

 

Since returning from the Christmas break, our team at The Exchange have shown good progress on level 4 with 50% of the concrete floor slab poured. During the next period we will be progressing level 5 concrete floor, precast columns, and precast twin wall cores A & B.

 

The Exchange Jan 22 (1)

 

While we are progressing the concrete frame, we will commence the SFS and glazing from the ground floor following the build sequence. Once this is wind and watertight, we will be looking at the internal fit out.

The Exchange - Build Update jan 22

 

 