The Exchange Build Update December 2021

As works continue on The Exchange, we are making good progress on level 3 having poured the first section of concrete floor slab. We are now 75% the way through installing the temporary works tables. 

 

The Exchange.4

Third floor concrete slab now installed

As we progress this level we are following on behind installing the precast double height columns to level 3 – 5 as well as tables to level 4. The stair and lift cores are also making good progress having been installed up to level 3, with the next delivery of twin wall panels level 3 – 4 due pre-Christmas.

 